t_wの輪郭
RSS
EV
2021/11/24 8:42:00
Earned Value
公共工事のEVの総和
Earned Value
Estimate At Completion
Schedule Variance
Cost Performance Index
Cost Variance
公共工事のEV
Schedule Performance Index
EV
EVM
earned
value
Earned Value
2021/9/28 16:50:00
プロジェクトのSカーブ
公共工事
EV
公共工事のEV
2024/7/16 11:50:00
公共工事のEVの総和
公共工事のEVM分析
cost
EVM
variance
CV
AC
EV
Cost Variance
2021/11/24 8:45:00
CV
=
EV
-
AC
cost
EVM
AC
EV
CPI
performance
Index
Cost Performance Index
2021/11/24 8:44:00
CPI
=
EV
/
AC
performance
EVM
SPI
EV
PV
schedule
Index
Schedule Performance Index
2021/11/24 8:47:00
SPI
=
EV
/
PV
EV
EVM
variance
SV
PV
schedule
Schedule Variance
2021/11/24 8:47:00
SV
=
EV
-
PV
EV
EVM
completion
AC
CPI
EAC
estimate
BAC
Estimate At Completion
2021/11/24 8:46:00
EAC
=
AC
+ (
BAC
-
EV
) /
CPI
公共工事
EV
公共工事のEV
公共工事のEVの総和
2024/7/16 11:51:00